TBP Project Paper - Progress Tracker MDP 2026 ACTUAL DATES · dQMS theme · Score 9/9 target (3/3/3)

Project: Plant-level dQMS at Toyota ASSB (COMP-G) Owner: Sir (Nizmax) TBP framework: BG-Step 1 (Theme) + BG-Step 6 (Project) + Step 7-8 (Final) Today: 15-Jun-2026 Stakes: Pass ≥ 2/3, target 3/3/3 Top score bonus: Nominated to Asia Top Executives
🔴 SIR IS IN "DEVELOP THEME" PHASE RIGHT NOW (11-30 Jun '26) — 15 days to develop the dQMS theme using TBP BG-Step 1. Next hard milestone: 1-9 Jul '26 (Supervisor + Approver sign), then 13 Jul (HR Home quality gate), then 14-15 Jul (TMA/ATL submit), then 16-31 Jul (REPORT THEME to Executive Panels, MS Teams, 10 min + 10 min Q&A) — ~31 days from today.

BLUF

Sir is on Phase 3 (Theme Confirmation). Theme Confirmation Report in 31-46 days. Final Report-Out in 123-137 days. Final Submission 11 Dec 2026. Certification Jan 2027. dQMS project paper = MDP project deliverable. Scoring 0-3 on Business Perspective, People Development, Attitude. Target 3/3/3.

Critical risk (this week): Sir's #1 TBP failure mode = stopping 5-Whys at Q2-3 + blaming operator. Theme will fail Theme Confirmation if not addressed. MUST land on process/system cause (QMS gate, not operator).

Critical path to Theme Confirmation (16-31 Jul): Fill real ASSB data (QMS system, paper traveler %, IATF 4 majors) + 1 gemba walk (paperless traveler station) + build 1-page theme slide + rehearse 10 min pitch 3x. All by 12 Jul.

MDP 2026 Timeline & Status

# Phase / Sub-event When Days Stakeholders Status Self-Score Open items / Next action
PHASE 1: PRE-WORK
1aEmergenetics Profile Test4-15 May '26pastParticipant DONE3 —
1bPre-Read MDP Case Study15 May - 5 Jun '26pastParticipant DONE3 —
PHASE 2: REGIONAL SESSION (THAILAND)
2Sharing & Workshop (3 days only)8-10 Jun '26pastParticipant DONE3 —
PHASE 3: THEME CONFIRMATION (TBP BG-Step 1) - 🔴 CURRENT
3aDevelop Theme (use TBP BG-Step 1)11-30 Jun '260-15 Participant + TBP Trainer + Supervisor NOW2 (target 3) • 1 gemba walk (paper traveler station) by 5 Jul
• 5-Whys Q5 (process/system cause, not operator)
• Real ASSB data placeholders filled
• POO w/ gemba evidence (date + names)
3bGet approval (Sup + Approver sign)1-9 Jul '2616-24 Participant + Supervisor + Approver PEND— • 1-page theme summary slide
• Pre-meet Supervisor + Approver for sign-off
3cHR Home final quality gate13 Jul '2628 HR Home PEND— • Submit to HR Home by 12 Jul (1 day buffer)
3dTMA/ATL review & submit14-15 Jul '2629-30 TMA/ATL PEND— • TMA/ATL: kenneth_ow@toyota-asia.com, piya_cha@toyota-asia.com
3eREPORT THEME to Executive Panels16-31 Jul '2631-46 Participant + Supervisor + Executive Panel PEND— • 10 min present + 10 min Q&A on MS Teams
• 15-min pitch rehearsed 3x with Q&A prep
PHASE 4: DEVELOP PROJECT (TBP BG-Step 6)
4aDevelop Project (8-section dQMS paper)3 Aug - 30 Sep '2649-107 Participant + TBP Trainer + Supervisor PEND— • Lit Review by 15 Aug
• Pillar 1, 2, 3 by 30 Sep
• Full TBP A3 v3.0 Kalyan strengthened
4bGet approval (Sup + Approver sign)1-12 Oct '26108-119 Participant + Supervisor + Approver PEND— • Project draft to Supervisor 1 wk before
4cHR Home final quality gate13 Oct '26120 HR Home PEND— • Submit to HR Home by 12 Oct (1 day buffer)
4dTMA/ATL review & submit14-15 Oct '26121-122 TMA/ATL PEND— • TMA/ATL verifies and submits to Panels
4eREPORT-OUT PROJECT to Executive Panels16-30 Oct '26123-137 Participant + Supervisor + Executive Panel PEND— • 10 min present + 10 min Q&A on MS Teams
• Final scoring 0-3 per criterion
PHASE 5: FINAL SUBMISSION (TBP Step 7-8) + CERTIFICATION
5aSubmit progress + implementation resultsBy 11 Dec '26179 Participant + Supervisor + Approver PEND— • Pilot dQMS results from 1 line
• Step 7 monitor + Step 8 standardize + yokoten w/ failure modes
5bTop Participants → Asia Top Executives(if applicable)— TMA/ATL PEND— • Auto if scored 3/3/3
5cAward certificationWithin Jan '27~200 TMA/ATL PEND— • Cert to qualified (≥2/3) participants

3 Scoring Criteria (Self-Assessment) - Target 3/3/3

# Criterion What scores 3 (Exceed) dQMS evidence in paper Self What to add for 3/3
1 Business Perspective Fact-based TBP, region-wide impact, breakthrough value across value stream Quantified COPQ savings, recall traceability 5d→30min, parent plant daily metrics, IATF re-cert pass, cross-A3 leverage (dQMS closes 4 findings) 3 • COPQ $$ baseline + projected
• Parent plant TMC quote
• 5-yr strategic fit (AI firm 2027)
2 People Development Team capability via coaching, feedback, learning environment, maximize potential Operator training on dQMS, certification, gemba culture shift, kaizen self-sustaining 3 • Training matrix (roles, tools, cert)
• # operators trained + certified
• Kaizen owner after implementation
3 Attitude Ownership, urgency, agility, networks, communication TBP/Jidoka/Andon embedded, gemba frequency, 5-Whys Q5 depth, yokoten w/ failure modes, reflection in TBP voice, cross-stakeholder work (ASSB↔JPJ↔TMC) 3 • 4-part Reflection in TBP voice
• Gemba frequency metric
• Yokoten w/ failure modes (not slogan)

Critical-Path Items for 3/3 (Kalyan R1-R5 + Sir's 3 failure modes + 2 new)

# Item Why it matters for 3/3 Status Phase Owner
R1State problem type (Setting/Reaching/Trouble)Panel checks firstDONE3aSir + BotBot
R2Label CMs Defensive/BR/BR-momentumMix tells the storyPEND3aSir
R3Owner name + Q-by date (no "team"/"TBD")"Team"=2, named=3PEND3aSir (provide names)
R4Pilot study + 26APF input connectionReport vs planPEND3aSir (with section head)
R5Reflection in TBP voice (not consultant)Attitude criterionPEND3aSir (in Step 8)
FM-15-Whys reaches Q5 (process/system cause)Sir's #1 failure mode (operator blame)PEND3aSir (verify w/ gemba)
FM-2POO explicit w/ gemba evidence (date+names)Sir's #2 failure modePEND3aSir (do gemba)
FM-3Target #+date+"why challenging"Sir's #3 failure mode (vague=BAU)PEND3aSir
NEWCross-A3 leverage (1 fix closes 4 findings)Unique system-thinkingDONE3aBotBot
NEWYokoten w/ FAILURE MODES (not slogan)What to AVOID sharedPEND4aSir

This-Week Critical Actions (15-21 Jun '26) - "Develop Theme" Window Opens

#ActionDueStatusNotes
1Review dQMS briefing (local 8096)16 JunPENDConfirm 3 pillars + 8-section structure + Kalyan R1-R5 all hit
2Schedule 1 gemba walk (paperless traveler station, ~30 min)By 22 JunPENDFor POO evidence (sir's #2 failure mode) - need date + names in A3
3Fill real ASSB data placeholders (QMS system, paper traveler %, IATF 4 majors)By 25 JunPENDWithout real data, Business Perspective score drops to 2
45-Whys draft: Q1-Q5, land on process/system cause (QMS gate, NOT operator)By 28 JunPENDSir's #1 failure mode. MUST end at process cause.
55 alternatives ruled out (operator carelessness, low motivation, random defect, bad supplier batch, equipment failure)By 28 JunPENDKalyan R1: 5 alternatives w/ evidence = strong R1
6Theme summary slide (1 page): headline + 3-pillar visual + cross-A3 leverage + AI firm hookBy 5 JulPENDFor 1-9 Jul approval gate
7Rehearse 10-min pitch 3x + Q&A prep (Why this theme? Why dQMS not other? What if pilot fails?)By 12 JulPENDFor 16-31 Jul Report Theme to Panels

Hard Reminder Schedule (for the report submission reminder system)

#ReminderWhenDaysWhat it tells sir
1Theme Confirmation: Develop Theme opens11 Jun 09:00past—
2Theme Confirmation: T-5 to develop window close25 Jun 09:00105 days to finish developing theme (11-30 Jun window). Push to Supervisor + Approver for sign-off.
3Theme Confirmation: T-5 to approval window close4 Jul 09:00195 days to get Sup + Approver sign-off (1-9 Jul window). Submit to HR Home by 12 Jul.
4Theme Confirmation: HR Home quality gate13 Jul 09:0028Today HR Home does final quality check. If not in HR Home by 12 Jul, theme will be late.
5Theme Confirmation: TMA/ATL submit window14 Jul 09:0029TMA/ATL submits to Executive Panels. After this, no more changes.
6Theme Confirmation: REPORT THEME to Panels (MS Teams)22 Jul 11:009Wed 22 Jul 11:00-11:30 AM MYT via MS Teams. 10 min + 10 min Q&A. Updated 13 Jul 2026 from Kenneth Ow (TMA) reservation.
7Develop Project: window opens (TBP BG-Step 6)3 Aug 09:0049Start writing 8-section dQMS paper. Lit Review by 15 Aug, Pillars 1-3 by 30 Sep.
8Develop Project: T-7 to approval window close5 Oct 09:001127 days to Sup + Approver sign-off (1-12 Oct window).
9Develop Project: HR Home quality gate13 Oct 09:00120HR Home final check. If not in by 12 Oct, late.
10Develop Project: TMA/ATL submit14 Oct 09:00121TMA/ATL to Executive Panels.
11Develop Project: REPORT-OUT to Panels (MS Teams)16 Oct 09:00123TODAY: 10 min + 10 min Q&A. Final scoring 0-3 per criterion.
12Final Submission: T-7 to TMA/ATL4 Dec 09:001727 days to submit progress (11 Dec '26 deadline). Pilot results + Step 7-8 ready.
13Final Submission: TMA/ATL deadline11 Dec 09:00179TODAY: Submit progress + implementation results to TMA(TH).
14Certification: TMA/ATL award certWithin Jan '27~200TMA/ATL awards certification to qualified (≥2/3) participants.