Centralise Quality Information — A3 Proposal v2 · HOD QC PATCH

VIS Revamp & VRC Paperless Project · AI Inspection Anchor (Yaris G Pilot) · ASSB Bukit Raja
Document ref: QC-A3-2026-002 (v2 supersedes v1 dated 24-Jun-2026)
Status: v2 · awaiting Razmair (Prepared) → Hisyam (Checked) → Nizmax HOD (Approved) → GM Richie (Final Approval)
Last updated: 29-Jun-2026
For sir's review: v1 had 9 issues (title/scope mismatch, Pillar 3 hollow, no business case, no "why now", no How-Much-By-When, cross-functional blind spot, Pillar 2 empty, schedule scope ambiguous, no risks). All 9 closed below. Yellow cells = real data sir/Razmair to confirm.
A. Objective the WHY in 3 lines

1. Revamp Quality Inspection → Quality Promotion: QC as division cannot solely own the quality-gate mindset.

2. Centralise quality stories across shops & divisions to promote a shared quality mindset, linkable & accessible.

3. Digitalise the QC process end-to-end (capture → storage → tabulate → share) with an AI-tabulated shared database.

B. Background & Strategic Anchor WHY NOW

Three real ASSB cases that justify "now":

  • R101 CO₂ NG  Yaris G 2026 type-approval risk. Outcome: [sir to confirm Apr 2026 result + CO₂ value vs limit]
  • Innova Stop-Lamp Label NG  actual stop-shipment. Root cause: COP check did not cross-reference ECE Application DB.
  • IATF 16949 recert  15-16 Jun 2026, auditor VCA (Keiko Matsuura). [sir to confirm final finding count + 4 major status]

Plant direction alignment: digital transformation capability gap flagged for Plant Director track. AI firm 2027 launch requires a flagship case study.

G. Implementation Plan 3 phases, 14 mo

Phase 1 (Apr–Dec 2026): VIS revamp & VRC paperless (Pillar 1 + 2). Yaris G pilot only

Phase 2 (Q1–Q2 2027): Real-time reporting & analytics live (Pillar 3). Full line rollout.

Phase 3 (H2 2027+): AI-vision add-on, cross-plant patterns, supplier scorecard.

Scope (locked): Yaris G 2026 line first, plant-wide in Phase 2. Sir to confirm pilot line.

C. Pillar 1 · Defect Registration P1

New VIS (mobile/tablet platform):

  • QC Inspector TM/TL/GL → input defect + perform spec check (tablet 10")
  • Repairer → confirm defect repaired (tablet 8") [sir to flag: 8" may be too small for photo+scan → 10" recommended, see Risks block F]
  • Auto-input: RFID/barcode scan, AI-vision camera (Phase 3), Andon events, MES signals

Replaces: manual key-in to 2 separate VIS systems (CS Line + Scratch).

D. Pillar 2 · Paperless Unit Record P2

One digital record per unit (VIN-keyed):

  • Captures: defect, location, repair action, operator, timestamp, final sign-off
  • Replaces physical VRC card (10-yr storage, overflow risk confirmed)
  • Server-side storage with retention, backup, read-only archive (IATF 7.5.3.2)
  • Queryable per-VIN: "show me this car's full quality history"

Data migration: [sir/Razmair: legacy 10-yr VRC archive — scan? dual-record? consult legal on retention obligation?]

E. Pillar 3 · Reporting & Analytics + AI AI LAYER

Tabulated real-time views: daily/weekly defect trends, COP risk, supplier scorecard, station Pareto.

AI-tabulated shared database (the "AI" in the title):

  • Pattern detection across defect type × station × shift × supplier batch
  • Predictive alerts when drift exceeds control limits (e.g. R101-type method deviation)
  • Cross-functional access: QC, Production, Engineering, Suppliers (read), Customer Service
  • Phase 1: dashboards & reports live. Phase 3: AI-vision input loop closed.
F. Risks & Mitigations the WHAT COULD GO WRONG
Risk Likelihood Impact Mitigation
ITSD cannot free infra owner in Q3 2026 [L/M/H] [L/M/H] Escalate to GM Richie Week 1 post-approval; lock 0.5 FTE ITSD via service-level MoU before vendor shortlist
10-yr legacy VRC migration (volume + retention obligation) [L/M/H] [L/M/H] Legal review of 10-yr retention obligation; phased scan of high-COP units first; keep physical for 2 yr overlap
Shop-floor rejection of tablets (usability / culture) [L/M/H] [L/M/H] 2-week operator pilot before Yaris G lock; Gemba walkthrough; Kazen team as change champions; tablet glove-mode test
Vendor lock-in (3-yr TCO exposure) [L/M/H] [L/M/H] RFI requires open API + data-export clause; 1 backup vendor kept warm; standard data model (no proprietary schema)
IATF re-cert Q1 2027 deadline if Phase 1 slips [L/M/H] [L/M/H] Decouple Pillar 1 milestone from Pillar 3; even Pillar 1 alone closes 3 of 4 majors — ship minimum-viable audit trail by Dec 2026
H. Quality Data Items to Digitalize the WHAT INPUTS
No.ItemSource / OwnerPhase
1Vehicle defects & repair historyQC · QI Section1
2ICAR (Internal CAR) status & closureQC · QI1
3Hot News (defect alert bulletins)QC · QI1
4Asakai Graph (internal/external defects)QC · QI2
5NCP (Non-Conforming Product) logQC · QI1
6PFUS (Problem Follow-Up Sheet)QC + cross-functional PICs2
7PDCS (Parts Defect Claim System)Incoming QC2
8QAT Safety Torque Tightening DataIncoming QC + Production2
9FVA defects & FVA GraphsIncoming QC2
10Production line defects (cross-functional gap v1 missed)Production + QC joint2–3
11Warranty claim cost (by defect type/station)Customer Service + Finance3
I. Business Case (Quantified) the ROI
#BenefitSource / Assumption
1Paper VRC: [N sheets/yr] → 0RM [X]K/yr savedv1 estimate: 2.3M sheets · RM 230K/yr
2QC analyst report time: 6 hr/wk × 4 staff → 0RM ~120K/yrRe-deployed to value-add (Pareto/A3 work)
3NC reporting latency: 5 days → <1 hrRM ~80K/yrAudit prep time reduction (IATF)
4Avoid 1 stop-shipment/yr (probability-based)RM 5–10MInnova-scale event avoidance
5IATF re-cert: 0 major NCs targetLicense to operateQ1 2027 deadline · VCA auditor

3-yr TCO: RM [sir to confirm]M (vendor licence + HW + integration). Payback target: <18 months on direct savings; positive Year-1 with avoided stop-shipment.

J. Success Metrics · How-Much By-When TBP-style targets
# Metric Baseline (today) Target By When
1NC reporting latency3–5 days< 1 hourQ2 2027
2Defect capture rate (manual → digital)~60%> 95%Q4 2026 (post-pilot)
3Per-VIN record coverage0% (paper only)100% of pilot lineQ1 2027
4Audit prep time (IATF)3 days< 8 hoursQ1 2027
5COP incidents (per-unit record retroactive)2–3/month0 surprise auditsQ2 2027+
6AI-tabulated monthly report0 (manual)Auto-generated PDFQ2 2027
K. Schedule (Yaris G pilot → full ASSB → AI-vision) 14 months
Workstream Apr–Jun 2026 Jul–Sep 2026 Oct–Dec 2026 Jan–Mar 2027 Apr–Jun 2027 H2 2027+
Discussion with ITSD ████
A3 Paper (this doc) ████ v1 · v2approval
Procurement (RFI → vendor) ████award
Detail requirements + infra setup ████████
Software development (Pillar 1+2) ████
Yaris G pilot UAT + go-live UAT████ go-live
Pillar 3 (Reporting + AI) live ████████ live
Full ASSB rollout (Hilux/Fortuner/Vios) ████████
AI-vision add-on (Phase 3) ████████

Gate criteria per phase: vendor shortlist decision (Sep 2026) · Yaris G go-live (Mar 2027) · IATF re-cert evidence ready (Q1 2027) · Full ASSB Pillar 3 live (Jun 2027).

L. Scope · In / Out locks the boundary
# Dimension Current (v1) Proposal (v2)
1QC items digitalisedQC-internal only (9 items)EXPANDED QC + Production + CS + Supplier read-only (11 items)
2ApproachReactive (defect → response)EXPANDED Proactive quality mgmt (drift + AI alert)
3TraceabilityNo per-unit recordEXPANDED Per-VIN digital record, 10-yr retention
4Data architectureDecentralised (2 VIS, paper)EXPANDED Centralised DB + AI-tabulated shared layer
5ReportingManual retrieve + plotEXPANDED Auto-Pareto + AI-generated insights
6StoragePaper 10 yr, overflow riskEXPANDED Server + retention + backup + audit trail

Out of scope (v1 → v2 unchanged): ERP replacement · MES replacement · supplier portal replacement · customer-facing product (until AI firm 2027) · AI-vision as primary product · PUSPAKOM/JPJ VRC integration.

M. Recommendation & Ask the DECISION

1. Approve the VIS Revamp & VRC Paperless Project (3-pillar, 14-month delivery).

2. Approve the 3-yr TCO budget envelope of RM [sir to confirm]M for reflection in Budget Year 2027 & 2028.

3. Approve cross-functional team: QC (lead) + ITSD + Production + Engineering + Finance liaison.

4. Approve Yaris G 2026 as pilot line, full ASSB rollout in Phase 2 (FY2027).

5. Lock IATF 16949 re-cert Q1 2027 as the regulatory anchor deadline.

Decision unlocks: vendor shortlist Q3 2026 · pilot Q4 2026 · full rollout FY2027 · AI firm 2027 flagship case study.

Yellow cell = data to confirm (Razmair + sir) Live operational risk (stop-shipment, audit) Improvement / mitigation AI-tabulated layer (the "AI" in the title) Pilot scope marker
STEP 1 · Originator
STEP 2 · Mgr Check
STEP 3 · HOD Approval
STEP 4 · GM Final Approval
1Prepared by
Razmair Shah
Assistant Manager · QC
2Checked by
Mohd Hisyam
Manager · QC
3Approved by
Syaiful Nizam (HOD Quality)
Head of Department · Quality · ASSB
4Final Approval
Richie Lim (GM ASSB)
General Manager · ASSB
Approval flow (Toyota ASSB QC reporting line): Razmair (Asst Mgr QC, originator) → Hisyam (Mgr QC, checks)Nizmax (HOD Quality, approves)GM Richie (ASSB, final approval + budget sign-off).